Tuesday, August 2, 2011

Small world


The next and hopefully last major milestone to get the Certificate of Occupancy is a working Septic system.  Francois used his manly tools to help uncover the holding tank and inspection ports. I called Ternoois, to see about the inspection. She was familiar with the process of working with the town, so that all sounded good to me. I gave her the address, and told her that according to my hand written notes they were the last to clean it out, and actually were the original installers.

Lady: Oh thats good, at least we know it was done right
Me: Yep, thats why I called you
Lady: So do you know who owned it before you?
Me: Hotchkiss
Lady: Laughing... oh if you look under the sink it says Ternoois. 
Me: Doubtful
Lady: Oh no I wrote it there
Me: Really?, well the bathroom has been changed, so you won't find it there.
Lady: We used to own that cottage.
Me: Wow small world. I checked out my earlier post about the ownership and indeed Ternoois owned it prior to Hotchkiss. 
Lady: Will it be difficult to get our trucks hose to the tank?
Me: Nope, drive in like you own the place and the tank is right there.
Lady: Thats good, we did one a couple weeks ago on the island, used like 200 feet of hose,  it was a terrible job. Just down the rode from you, Jack McGuire. It was really hard to do. Did another McGuire too, it wasn't near as bad as Jack's.
Me: I am sure there was a lot to pump out.  




Bedrooms.... Check!


Both bedrooms are now available for the interior decorator. Bathroom is all done too.  Yay!

Francois working !

Oh yeah we have a bed

Saturday, July 30, 2011

Plate rack installed

These kids are growing like weeds

Actually Francois and I tried to find the septic cover, we gave up after our third hole. Tomorrow we use a machine

Tuesday, July 26, 2011

Random photos

Francois' Stucco Getting Painted
Interesting Light 
Detail of Exterior Light
Lead Flashing 

Monday, July 25, 2011

Thanks

Cindy & I just wanted to thank everyone for the help this weekend. Like any project the closer you get to the end, the more you see that needs to be done.

Immediate Goals
1) Be able to say the bedrooms are done. (hang doors, fix paint boo boos, shoe molding)
2) Be able to say bathroom is done. (paint trim)

On deck
1) Kitchen drawers/doors
2) Fire Place plug/remove drywall/clean
3) Buttery plywood

Horizon
1) Finish Living Room floor
2) Shoe Molding
3) Install Oven in Buttery
4) New Roof/Gutters

Dream
1) Stock Kitchen
2) Finish Buttery
3) Exterior Paint
4) Landscaping

Saturday, July 23, 2011

Update

Passed final electrical inspection!
Hot water plumbed!
Kitchen sink up and running, argh for short connections that hide behind a sink.

I told Cindy that this could likely be last time I ever sweat copper. I was thinking there would be little opportunity and that PEX had really taken over the plumbing technology world. She said don't count on it, she had been scoping out new fix-it-uppers recently and found some charming cottages that just needed a little attention. Somehow I see a few more dumpsters in my future and the plumbing torch won't be put in the back of the cabinet.